DISTRESS IN THE TARMAC
- From: gay <$fckgay@xxxxxxx>
- Date: Mon, 12 Mar 2007 07:45:19 +0800
Perspective >> Sunday March 11, 2007
DISTRESS IN THE TARMAC
Because the airport site is located in the floodway of Bangkok's eastern
suburbs, it requires both effective flood protection and drainage systems to
avoid problems caused by water seepage into the sand blanket under the airport's
taxiways and runways, writes PROF WORSAK KANOK-NUKULCHAI
Last October, when the first sign of rutting was spotted in five of the six
taxilanes and in one taxiway at the Suvarnabhumi International Airport, the
Engineering Institute of Thailand (EIT) assigned a team of experts to join the
preliminary investigation. The investigation revealed that the damage was caused
by the premature failure of asphalt base course due to the separation of asphalt
binder from aggregate surface in the presence of moisture, commonly known as
"stripping". It was quite evident from the milled damage area that water seeped
from the sand blanket underneath the cement-treated base (CTB) through expansion
joints.
The key question is: How, and also how long, has the water been trapped in the
sand blanket?
This article intends to provide technical facts to the readers who want to
understand what really happened to the airfield pavement of this brand new
airport.
Figure 1: Typical distress in the taxiways and taxilanes.
WORRYING OBSERVATIONS
On 27 October 2006, about 2-3 weeks after the official opening of the airport,
the first signs of distress were spotted at several locations in the taxiways
and taxilanes, in the form of rutting, rutting with shattering and split, and
rutting with hairline cracks (figure1). Since then, a similar pattern of failure
has developed heavily in five of the six taxilanes and along the east parallel
taxiway. Although both runways are still in good structural condition, plastic
deformation of the asphalt wearing course was observed near the takeoff
position. The extent of the damage is summarised in the table above.
Suvarnabhumi airport covers an area of 20,000 rai (3,200 hectares). In its first
phase, the airfield serves its hourly 112 flights with two runways, six taxiways
and six taxilanes. The tarmac consists of three layers of asphalt concrete,
namely the base course (23 cm thick), the binder course (6 cm thick), and the
wearing course (4 cm thick). Underneath are four layers of the cement-treated
base (CTB), 18 cm. thick each, sitting on top of the sand blanket (approximately
80 cm thick) left over from the ground improvement process.
Excavation to test the connectivity of the trapped water.
Plastic deformation was observed on the wearing course at the turn-around
segment of the taxiway leading to the takeoff position of the runway (Figure 2).
This location is normally under maximum load when the plane takes off with a
full load of fuel. The high shearing stress that causes plastic deformation was
imposed by braking, accelerating or turning traffic. Plastic deformation is
greatest at high temperatures, especially for the AC 60/70 binder grade used in
this case. The occurrence of the plastic deformation at this location is
therefore a common phenomenon and only routine maintenance is required to repair
this type of distress. Aside from this surface distortion, both runways are in
good structural condition.
Initial investigation was made by coring the asphalt concrete pavement at a
diameter 100 mm throughout its 33 cm thickness from the damaged areas (Fig. 3).
The following observations can be made:
- All core samples from damaged area show evidence of asphalt stripping at the
base course, a typical effect of soaking water, while core samples from
undamaged areas show good condition.
- The water had infiltrated into and confined in the asphalt concrete base
course for a long period. Thus, the base course has been immersed in and
impaired by the water.
- As a result of asphalt stripping, asphalt binder was separated from aggregate
surface, leading to premature loss of strength and stability of the base course.
- The load of the aircraft had then impaired the failed asphalt concrete
pavement, causing rutting on the surface.
Based on the core samples, laboratory tests have indicated the correct job mix
and aggregate gradation of the asphalt concrete material. This was also
confirmed by a separate test at the Highway Department.
To expose the cement-tested base (CTB) for visual inspection, an area of asphalt
concrete pavement was milled at the damaged area of the taxilane. It was evident
that there was no sign of damage or subsidence in the CTB. However, traces of
water seepage were clearly observed (Fig 3) along the rim of the expansion
joints in the CTB. This evidence of seepage further hinted that a large quantity
of water might still be trapped in the sand blanket.
On January 31, a test pit (Fig 3) was dug on Taxiway T11, where damage was found
to be extensive. After the excavation went through CTB and exposed the top
surface of the sand blanket, water seeped through the sand immediately until the
water level reached about 20 cm above the sand blanket (or roughly at +0.0 MSL).
The water stayed at that level even when attempt were made to clear the water.
Interestingly, to prove that water in the sand blanket is fully confined with no
connection outside, a deep excavation was made nearby, but outside the pavement
area. After the excavation, the dug hole was completely dry. No sign of water
from the sand blanket had receded into this empty hole.
Meanwhile, Highway Department experts have tested the samples of sand and CTB
from this test pit and reported that all materials tested have met the
standards.
Figure 2: Surface deformation of the runway.
HOW WAS THE WATER TRAPPED?
Based on the official report of the investigation committee appointed by
Airports of Thailand Public Company (AOT), the following reasons had been given
for the trapped water:
1. Runoff of rainfall water was collected and retained within the airport
compound in the pockets of sand used to fill fishponds, swamps and waterways
prior to the airport construction. Water from this source might find its way
into the sand blanket.
2. Surface water spilled from the drain age canals, during the flooding period,
over the top soil around the unpaved neighbourhood into the sand blanket.
Figure A1: Natural and consolidated soft clay deposits.
3. Surface water once trapped underground was not able to escape due to the lack
of a subsurface drainage system. This was aggravated by the blockage of culverts
and other underground structures.
4. Based on soil boring records, thin sand layers may exist originally within
the soft clay layer at a level about 10 metres deep. Some of these sand layers
may cross path with the leftover PVD, thus allowing running shallow ground water
to seep upward into the sand blanket.
On the last point, some geotechnical experts argued against this possibility. At
the end of the PVD preloading, the extra surcharge consisting of crushed rocks
was removed. Thus, it is no longer possible for water to move up to the surface
through the PVDs against the hydraulic gradient and against gravity at the end
of consolidation process.
Figure A2: Consolidation process of soft clay under the airfield pavement.
In addition, there is hydraulic back-pressure from the trapped water in the sand
blanket making it impossible for such hydraulic upward flow to occur.
Because the airport site is located in the floodway of Bangkok's eastern
suburbs, it requires both effective flood protection and drainage systems. The
aim is to prevent flooding from flash floods, as well as to drain away rainwater
in the catchments of the airport compound. The design of the polder system
includes the perimeter polder dike, internal drainage system, two pumping
stations and a perimeter road (Fig 4).
Basically, the internal drainage system for runoff water consists of:
1. The unlined primary canals and reservoirs both with the bed at -1.90 m MSL.
Based on the design criteria, water level in the primary canals and reservoirs
must be maintained not higher than -1.40 m MSL.
2. The secondary canals with concrete linings. The canal bed of the secondary
canal is -1.15 m MSL. It is designed to be dry except during the raining.
The primary and secondary canals are interconnected by ditches to ensure that
the runoff water from the pavement area will flow under gravity towards the two
pumping stations located at the south corners of the site. In the operating
manual, water in the primary canals and reservoirs must always be controlled at
the pumping stations to ensure that the water level is maintained at -1.40 m MSL
or lower.
With the design assumption that no rain water runoff can leak into the sand
blanket, no subsurface drainage system exists to systematically drain trapped
water from the sand blanket. This might be a weakness in the design criteria of
the airfield pavement.
Figure 3: Illustration of milled pavement in the taxilane T11, a core sample of
asphalt concrete, trace of the water seepage at CTB joint and the test pit.
WHAT'S NEXT?
In its press release issued on 15 February 2007, the Engineering Institute of
Thailand (EIT) strongly recommended that, similar to a first-aid treatment,
trapped water should be drained out urgently to minimise the potential spread of
cracks on taxi lanes, taxiways, and even on runway. This immediate action should
be carried out with the consent and cooperation of all concerned parties
including the project management consultants, the designers and the contractors.
Alternatively, the AOT should seek temporary protection from the court to
implement the required first-aid treatment without damaging its rights under the
contract. Meanwhile, it was reported that the AOT plans to commission a team of
international experts to carry out an in-depth technical investigation in order
to recommend long-term remedies.
Prof Worsak Kanok-Nukulchai, PhD is dean of the School of Engineering &
Technology at the Asian Institute of Technology. He is also vice-president of
the Engineering Institute of Thailand and a member of the Royal Institute.
Illustration of taxiways and taxilanes.
GROUND IMPROVEMENTS
Suvarnabhumi Airport compound is situated on formerly agricultural land, fish
farms, swamps and waterways. A thick deposit of soft clay is found over 10
metres deep, with 100-120% water content, on top of medium stiff clay and stiff
clay with water content of 50-90% and less than 50% respectively.
Soil is a multiphase system, comprising a solid phase (soil particles) and a
fluid phase (air and water) called the pore fluid. For soft clay, the higher the
volume of the fluid phase, the weaker and more compressible the soil mass.
Therefore, any reduction of water in the pores of the soil, which decreases the
volume of the soil mass (Figure A1) and subsequently increases the
particle-to-particle contact, increases the strength of the soil and reduces its
compressibility at service stage.
To be suitable for airfield pavement, pore water in the soft soil must be
squeezed out to result in water content around 80%. Thus, the soft clay is
transformed into medium stiff clay. This consolidation process can be
accelerated by a modern technique using Prefabricated Vertical Drains (PVD).
PVD is a plastic tube core wrapped in a filter jacket, made of non-woven
polyester or polypropylene geotextiles or synthetic paper. PVDs drain soil by
squeezing out pore water, a process that can be accelerated by adjusting the
spacing of PVDs. In this process, water flows a lot more quickly horizontally
towards the drain and then vertically along the drains towards the permeable
drainage layer at the top. The step-by-step procedure of consolidation using PVD
is illustrated in Figure A2.
Figure 4: Profile of the flood protection and the drainage system.
Overview of east runway, taxiways and the drainage system.
.
- Prev by Date: Empowering 'bad girls'
- Next by Date: The tree of death
- Previous by thread: Empowering 'bad girls'
- Next by thread: The tree of death
- Index(es):
Loading