Re: When mixing on site, how much concrete could one guy pour and finish in one day?
- From: dpb <bozarth.d@xxxxxxxxx>
- Date: 7 May 2007 07:52:41 -0700
hallerb@xxxxxxx wrote:
On May 7, 10:21?am, "** Frank **" <noem...@xxxxxxx> wrote:
With a small electric concrete mixer (2 bags of 60# or 80# ready mix at a
time) I'm not able to mix much more than an area of 6' x 12' by 4" thick,
anymore I'm not able to finish before it sets in. That was about 44 bags of
60# of ready mix.
Would having two small mixers on at the same time increase productivity? I
don't think I could, or want to, do more than 100 60# bags day.
your losing fiancially, for larger quanties your better off getting it
ppre mixed by a truck.
I'll concur -- or get a larger mixer (and more importantly, a buddy or
two) and buy the cement and aggregate/sand and mix it from scratch...
.
- References:
- When mixing on site, how much concrete could one guy pour and finish in one day?
- From: ** Frank **
- Re: When mixing on site, how much concrete could one guy pour and finish in one day?
- From: hallerb@xxxxxxx
- When mixing on site, how much concrete could one guy pour and finish in one day?
- Prev by Date: Re: When mixing on site, how much concrete could one guy pour and finish in one day?
- Next by Date: Re: Craftsman Tractor Problem
- Previous by thread: Re: When mixing on site, how much concrete could one guy pour and finish in one day?
- Next by thread: Re: When mixing on site, how much concrete could one guy pour and finish in one day?
- Index(es):
Relevant Pages
|